Two berms — north and south — are shown on the Akkerman farmland in Red Rock Township. This summer, the Cedar River Watershed District plans to build the berms to help reduce flooding and improve water quality as part of its ongoing Capital Improvement Plan (CIP) initiative.

Two berms set for 2023 in Dobbins

CRWD to build upland storage for stormwater in creek’s south branch headwaters

Cedar River Watershed District
5 min readMar 31, 2023

--

March 31, 2023 — Spanning a quarter-mile in length each, two berms planned for a nearly $1 million project in the headwaters of Dobbins Creek’s south branch will play a big role in reducing floods and improving water quality.

Cedar River Watershed District soon will seek bids for construction this summer of the earthen berms six miles east of Austin in Red Rock Township on cropland owned by farmer Al Akkerman. It is north of Interstate 90 and east of Mower County Road 19.

About 60 percent of the project’s funding will come from the state’s Clean Water Fund, with the rest mostly covered by a grant from The Hormel Foundation in Austin. A small portion will be funded by a federal Environmental Protection Agency grant.

Combined, the dams will provide temporary storage for stormwater running off 467 acres of mostly cropland.

“We definitely will make good progress toward our goals when these berms are in place,” said Cody Fox, CRWD’s administrator and project manager. “We’re grateful for Mr. Akkerman’s willingness to work with us on the plans.”

CRWD’s Board of Managers approved the project’s plans at its March 22 meeting. This project is a continuation of CRWD’s Capital Improvement Plan (CIP) started in 2016 to build structures that capture large amounts of stormwater and slowly release it. This decreases the amount and speed of stormwater flow, reducing the potential for major streambank erosion downstream.

With upland storage, much of the sediment, excess nutrients and other pollutants in stormwater settles to the bottom of the basin behind the berms rather than continue into Dobbins Creek, East Side Lake and the Cedar River.

With the Akkerman site, the berms will be the first built under CRWD’s second CIP phase. A north berm will be 1,500 feet in length with a peak height of 12 feet; the south berm will be 1,250 feet long and 10 feet high.

CRWD’s upstream berm for its Dobbins 1 project holds back a significant amount of stormwater water in September 2019 following heavy rainfall.

CRWD’s first CIP phase had a goal of an 8 percent peak flow reduction, which was achieved with a $3.2 million grant from The Hormel Foundation and another $3.4 million in state and local funding that built 14 projects, including 11 upland-storage structures in the Dobbins watershed.

In 2020, CRWD built its most-recent CIP project also in the headwaters of Dobbins’ south branch. That $1.2 million project created a nearly 2,000-foot-long berm in Dexter Township, with a 21-foot peak height.

Officials from CRWD and the Minnesota Board of Water & Soil Resources (BWSR) talk with media in September 2021 at the largest upland-storage berm built to date by the CRWD as part of its Capital Improvement Plan (CIP). This berm is located in Dexter Township in the headwaters of Dobbins Creek’s south branch.

When the Akkerman berms are finished, CRWD’s upland-storage projects in the Dobbins watershed will treat stormwater coming from 3,967 acres of mostly cropland, which is nearly 6.2 square miles. The projects also will have the combined ability to temporarily hold up to 410 million gallons of stormwater when levels reach each berm’s spillway.

For perspective, Austin’s largest water tower — on the west side of town — holds 1 million gallons of water.
With the two berms, CRWD’s overall system of CIP upland structures will provide a 14-percent reduction in stormwater flows during what’s known as a 100-year flood event, which has a 1 percent chance of happening every year, Fox said.

“It doesn’t sound like a lot but that reduction really can make a big difference,” Fox said.

Above and below are hydrographs showing the significant decline in stormwater flows during a 100-year rain event at the location of the two berms planned for construction this summer by CRWD.

A few years ago, CRWD’s CIP projects achieved a 10 percent reduction that equals a nearly 1-foot drop in Dobbins’ peak flows at Austin’s Jay C. Hormel Nature Center when the area experiences a 10-year rain event or roughly 4 inches of rain. With such a rain storm, some rural roads can become overtopped with flooding, particularly in the flashy Dobbins watershed, Fox said.

Red Rock Township’s 230th Street bridge overtops by the South Branch of Dobbins Creek in March 2019 during a major snowmelt.

CRWD officials also are optimistic that any bonding bill passed this spring by the state Legislature will include a significant amount of funding for future CIP projects in the Dobbins watershed.

East Side Lake, a stretch of Dobbins Creek downstream from the nature center that was created by a dam and a manmade lake basin, benefits from CIP projects keeping less sediment or earthen material from fields, roads and streambanks from flowing into it.

“As we keep doing these projects in the headwaters,” Fox said, “we hope to reach a point where the state will determine that Dobbins Creek can be delisted for being impaired for sediment. That also will mean the creek has much better water quality.”

Austin City Council member Oballa Oballa talks with CRWD watershed technician James Fett in June 2021 at the outlet of CRWD’s biggest upland-storage structure during a special visit by the council to view the CIP berms upstream from the City of Austin.

--

--

Cedar River Watershed District
Cedar River Watershed District

Written by Cedar River Watershed District

Formed in 2007, CRWD works to reduce flooding and improve water quality on the Cedar River State Water Trail and its tributaries in southern Minnesota.

No responses yet